INSTALLATION

Cast-In Place Installation
1. Attach anchor straps
a. Floor doors for concrete pour applications are provided with 1"x4"x1/8"
masonry anchors as shown. Anchors will need to be bolted on prior to install.
2. Square the frame
a. It is vital that the frame remains square and level during the concrete pour.
3. Set the frame in the opening
a. Secure the floor door into the desired area with welding, bolting or other
anchorage, making sure not to interfere with the operation of the hatch.
4. Protect exposed aluminum from cement
a. To ensure a good quality installation and prevent staining, alkaline building
materials such as cement should be removed quickly from aluminum surfaces.
2-hr cast in detail
*3-hour rating available on Diamond Tread and 1/8" Pan Doors only.
Great Products. Better Partners.
Babcock-Davis is a leader in roof hatches, smoke vents and safety railings for the commercial roofing market. We also
manufacture architectural access and safety-related building products for commercial structures. Babcock-Davis provides
local connections through a broad distribution network to accelerate and simplify the building process for contractors and
building owners, offering hassle-free services including access to technical experts, REVIT tools for BIM, HPDs for LEED v4, 3-
part specifications and AIA-accredited continuing education courses.
courses.
Open in this position
2-hr alt cast in detail
Installation & Operation + Maintenance
Do not open in this
position
3-hr cast-in detail*