® TORK DIN101B & DIN201B Operating Instructions KEYPAD Start program input Hand switch Set time, ¹ Prog. end program 2 channel input units only Select day(s) Selects Signal, of the week Duty Cycle Clear Res. Delete events switching time...
Page 2
button, and then press the “Reset” button. The entire display will be shown, and the unit will change from one to the other each time you press the reset button. 00:00 = 24 hour format 12:00 = 12 hour format Resetting the Unit We suggest that when installing the unit, press the “Reset”...
Page 3
5: To set the current month, press the “m” button. To set the current date, press the “h” button. The display is in “MM DD” format – for exam- ple, July 4 is displayed as “07 04”. 6: When you have set the desired date, press “Prog.”...
Page 4
2: When you have set the desired date, press “Prog.” to store it. The unit automatically calcu- lates the day-of-the-week, in which the changeover occurs. So if you have entered the last Sunday in October, the unit will remem- ber, and update this day each year. 3: When you finished setting the current date, and the beginning and the end of daylight sav- ings time, press the ¹...
Page 5
When you have set the desired time, press the ¹ button to store it in memory, and go back to run mode. Setting schedules for programmed load events 1: In the run mode, press the “Prog.” button. We will assume that no previous events are set. The following display will be shown.
Page 6
6: Repeat steps 2-5 for as many schedules as you need. When you have finished setting the programs, press the ¹ button to return to execute schedules. For 2 channel DIN201B only The loads can be programmed either individual- ly, or simultaneously. An “on” event for one load can also be an “off”...
Page 7
once. A symbol appears on the screen. 5: Press the “Prog.” button to confirm the signal event. 6: Press the “m” button to toggle the signal dura- tion between minutes, or seconds. 7: In this example, we will set a signal duration of 7 seconds.
Page 8
4: To select duty cycle, press the button twice. A appears on the screen. 5: Press the “Prog.” button to confirm the duty cycle. 6: Press the “m” button to toggle the on time duration between minutes, or seconds. 7: In this example, we will set an on time duration of 5 minutes.
Page 9
C. If you want the duty cycle to continue endlessly, there can not be any other events in the unit’s memory. Override the load status Load status can be overridden by the user. Pressing the button in the run mode overrides the channel from it’s programmed state.
Page 10
time, active days, or event status by pressing the appropriate buttons. When you have made the desired changes, press the “Prog.” button to store them, and to proceed to the next schedule. Press the ¹ button to return to run mode.