9 Installation in piping
Tools
▶ The tools required for installation and assembly are not
included in the scope of delivery.
Use appropriate, functional and safe tools.
1. Ensure the product is suitable for the relevant application.
2. Check the technical data of the product and the materials.
3. Keep appropriate tools ready.
4. Wear appropriate protective gear, as specified in the plant
operator's guidelines.
5. Observe appropriate regulations for connections.
6. Have installation work carried out by trained personnel.
7. Shut off plant or plant component.
8. Secure plant or plant component against recommission-
ing.
9. Depressurize the plant or plant component.
10. Completely drain the plant (or plant component) and let it
cool down until the temperature is below the media vapor-
ization temperature and cannot cause scalding.
11. Correctly decontaminate, rinse and ventilate the plant or
plant component.
12. Lay piping so that the product is protected against trans-
verse and bending forces, and also from vibrations and
tension.
13. Only install the product between matching aligned pipes
(see chapters below).
14. Please note the flow direction (see chapter "Flow direc-
tion").
15. Please note the installation position (see chapter "Installa-
tion position").

9.3 Installation with clamp connections

Fig. 1: Clamp connection
Gasket and clamp
▶ The gasket and clamps for clamp connections are not in-
cluded in the scope of delivery.
1. Keep ready gasket and clamp.
2. Carry out preparation for installation (see chapter "Prepar-
ing for installation").
3. Insert the corresponding gasket between the body of the
product and the pipe connection.
4. Connect the gasket between the body of the product and
the pipe connection using clamps.
5. Re-attach or reactivate all safety and protective devices.
GEMÜ 567 BioStar control
NOTICE
NOTICE

9.4 Installation with butt weld spigots

Fig. 2: Butt weld spigots
1. Carry out preparation for installation (see chapter "Prepar-
ing for installation").
2. Remove the actuator before welding the valve into the
plant (see chapter "Removing the actuator").
3. Adhere to good welding practices!
4. Weld the body of the product in the piping.
5. Allow butt weld spigots to cool down.
6. Mount the actuator on the valve body (see chapter
"Mounting the actuator").
7. Re-attach or reactivate all safety and protective devices.
8. Flush the system.