Ups Schedule - NXT Power VANGUARD THREE-PHASE 10-40 KVA UPS SNMP Manual

Table of Contents

Advertisement

6.3

UPS Schedule

This function let user to configure the UPS operation mode and battery test
schedule.
The calendar shows the scheduled tasks.
Click "Setting" button to configure the schedule of each task.
UPS Schedule
Index
This field shows the index numbers of the table entries.
Control
To Enabled/Disabled this task.
Repetition
Once: Execute this task only one time.
Weekly: Execute this task every week.
Date
The first execution day
Time
The execution time
Task
Select the UPS operation mode that wants to execute.
Shutdown Delay Time
The delay in seconds the UPS remains on after being told to shutdown.
*This parameter is only for the UPS Schedule Shutdown.
Battery Test Schedule
Control
To Enabled/Disabled the battery test function.
Date
The first execution day
Time
The execution time
Repetition
Configure the repetition time in week.
14

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the VANGUARD THREE-PHASE 10-40 KVA UPS SNMP and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents