Installation Conduit Plan - Power And Communication Circuits - Duracell D-HUB Installation Manual

Table of Contents

Advertisement

2.2 Installation conduit plan – power and communication circuits
The following example outlines the conduit plan for power and communication circuits for a complete solar plus
storage system using the DURACELL HUB and the DURACELL POWER CENTER 5KW. (String PV inverter shown –
replace with equivalent AC combined micro-inverter output, where applicable).
Figure 9: Installation conduit plan for a solar plus storage installation (base model shown).
Table 1: Circuit summary for a solar plus storage installation.
Conduit
Circuit Definition
Ref
P1
ESS grid power
P2
ESS backup power
P3
Main panel power
P4
Backup panel
P5
Solar PV power
EMS communication cable
S1
3 meter patch cable included
S2 (x2)
CT , 50 Amp 8 ft pigtail
AK1 Hub Control Signal cable
S3
harness included , 10 ft
S4 (x2)
CT, 200 Amp 8ft pigtail
S5
CT , 50 Amp 8 ft pigtail
Note 1: Conductor type referenced where Hub is installed greater than 24" from the ESS. Signal wiring routed in
conduit with power must be 300V rated. For runs longer than 10 meters, signal separation from power is
recommended to minimize signal interference.
Disclaimer:
Manufacturer supplied components represented here are limited to the PCS/Battery, DURACELL HUB, and CTs for PV, battery, and
mains. All other materials and components represented are customer supplied. CEC/NEC electrical code compliance is the
responsibility of the designer and/or electrical permit holder. Source circuit disconnects for PV and ESS grid/load ports not shown.
CT home
Conductor
Circuit Protection
(recommended)
8/3
40 Amp
8/3
40 Amp
8/3
40 Amp
40 Amp feeder if total backup ccts exceed 40
8/3
Amp/240V rating
8/3
40 Amp
CAT 5/6 STP
-
-1
18/2, 300V
-
18/2, 300V
-
-1
18/2, 300V
-
-1
18/2, 300V
-
CT 50A: (2x)
6