4 Mechanical Mounting
Step 2 Lift and move the inverter to the destination by using the side and bottom handles as well as the four installed
hand shanks.
Step 3 Remove the four hand shanks .
Inappropriate moving operation may cause personal injury!
• It is recommended that at least four installers carry the inverter together and wear
protective equipment such as smash - proof shoes and gloves.
CAUTION
• Always beware of the gravity center of the inverter and avoid tipping.
The ground surface on which the inverter is to be placed should be covered with a
sponge pad, foam cushion or the like to prevent the inverter bottom from scratches.
NOTICE

4.3.2 Hoisting Transport

Step 1: Install two M12 lifting eye nuts into the corresponding M12 holes at side handles of the inverter.
Step 2: Lead the sling through the two lifting eye nuts and fasten the tie-down strap.
Step 3: Hoist the inverter, and stop to check for safety when the inverter is 100mm above the ground. Continue
hoisting the device to the destination after ensuring the safety.
Step 4: Remove the two lifting eye nuts.
Keep the inverter balanced throughout the hoisting process and avoid collisions with walls or
other objects.
CAUTION
Stop hoisting in the event of severe weather, such as heavy rain, thick fog, or strong wind.
The lifting rings and the sling are not within the delivery scope.
FIG 4-6 Transport hole location diagram
FIG 4-7 Lifting and handing schematic diagram