4: INITIAL TURN ON AND ACCEPTANCE PROCEDURE
4.1 GENERAL
This chapter provides the initial turn on and acceptance procedures for the AC Distribution
Shelf.
Note: Pull all distribution fuses/set all CB's to OFF prior to performing the operational
checkout procedure.
Step
Ohm wires from AC Distribution Shelf to the Inverter Shelf to ensure
1.
proper connection.
Ohm wires from AC Distribution Shelf to Loads to ensure proper
2.
connection.
3.
Apply input DC to the Inverter Shelf.
Perform the operational test of the
4.
Inverter Shelf per manual 4380419PD
5.
Remove all tools and test equipment.
5: AC DISTRIBUTION PANEL RATINGS
Part Number
6180498P (23" For Conduit)
6180529P (23" W/Outlets)
6180542P (19" For Conduit)
6180533P (19" W/Outlets)
Page 15
© Copyright 2021 ABB. All rights reserved.
Description
Maximum Current Rating
200 Amps
180 Amps
100 Amps
100 Amps
Pass/Fail
Initials
Voltage Rating
Maximum Circuit Breaker Rating
120VAC
70 Amps per circuit position
120VAC
15 Amps per circuit position
120VAC
70 Amps per circuit position
120VAC
15 Amps per circuit position
Date