Dispatch and storage
4.1

Condition on delivery

The factory-assembled circuit-breakers on
withdrawable parts are checked at the
works for completeness of the equipment
installed and simultaneously subjected to a
routine test in accordance with GB/T 11022
GB 1984, IEC 60694,DIN VDE 0607 IEC
publication 62271-100, thus verifying their
correct structure and function.
4.2

Packaging

The circuit-breakers on withdrawable parts
are mounted individually on wooden pallets and
sealed in film and/or packed in cardboard for
delivery.
Packaging for overseas shipment:
Drying agent bags inserted in the film-
sealed packaging.
4.3

Transport

Loading of the package units must only be carried
out with a
crane,
fork-lift truck and/or
trolley jack.
CrB
Figure 4/1: VD4 breaker on withdrawable part
Only handle by crane when the transport bracket
147 and crane harness are fitted.Always bear in
mind that the high situated centre of gravity may
induce the breaker to tip over!
50.2 Front partition plate (Do not stress this plate)
147
Transport bracket (TK)
148
Transport profile (TP)
CrB
Crossbar
18
Notes:
Avoid impact during handling.
Do not subject to other damaging mechanical
stresses.
Lifting gear must not be attached to the breaker
poles or parts of the operating mechanism.
When moving the withdrawable part only use
the sliding handles 51.2 (e.g. for racking
in/out the circuit-breaker unit into/out of the
switchgear panel or for the transport of
the unit in the switchgear room). Do not
bring any force on the front partition plate 50.2
of the withdrawable part.
Only handle the modules by crane with bolted-
on transport brackets 147, suitable lifting
ropesand crane harness.
Ensure that the circuit-breaker unit on
the withdrawable part, with its relative high
situated centre of gravity, cannot tip over when
moving it by crane or fork-lift truck, or when
handling it outside the switchgear room.
Figure 4/2: VD4 breaker for fixed installation
Only handle by crane when the lifting lugs are fitted.
Always bear in mind that the high situated centre
of gravity may induce the breaker to tip over!