COMPLETE INLET AND OUTLET PLUMBING
Measure, cut, and loosely assemble pipe and fittings
from the main water pipe to the inlet and outlet ports of
the water softener valve. Be sure to keep fittings fully
together, and pipes squared and straight.
Be sure hard water supply pipe goes to the water
softener valve inlet side.
NOTE: Inlet and outlet are marked on the water softener
valve. Trace the water flow direction to be sure
hard water is to inlet.
IMPORTANT: Be sure to fit, align and support all
plumbing to prevent putting stress on the
water softener valve inlet and outlet.
Stress from misaligned or unsupported
plumbing may cause damage to the
valve.
Complete the inlet and outlet plumbing for the type of
pipe you will be using.
INSTALL VALVE DRAIN HOSE
1. Measure, cut to needed length and connect the 3/8"
drain line (provided) to the water softener valve drain
fitting. Use a hose clamp to hold the hose in place.
NOTE: Make the valve drain line as short and direct as
possible.
IMPORTANT: If codes require a rigid drain line see
"Valve Drain requirements" section.
2. Route the drain hose or copper tubing to the floor
drain. Secure drain hose. This will prevent
"whipping'' during regenerations. See "Air Gap
Requirements" section.
INSTALL SALT STORAGE TANK OVERFLOW
HOSE
1. Measure, cut to needed length and connect the 3/8"
drain line (provided) to the salt storage tank overflow
elbow and secure in place with a hose clamp.
2. Route the hose to the floor drain, or another suitable
drain point no higher than the drain fitting on the salt
storage tank (this is a gravity drain). If the tank
overfills with water, the excess water flows to the
drain point. Cut the drain line to the desired length
and route it neatly out of the way.
IMPORTANT: For proper operation of the water
softener, do not connect the water
softener valve drain tubing to the salt
storage tank overflow hose.
Installation Instructions
TEST FOR LEAKS
To prevent air pressure in the water softener and
plumbing system, complete the following steps in
order:
1. Fully open two or more softened cold water faucets
close to the water softener, located downstream
from the water softener.
2. Place the bypass valve (single or 3 valve) into the
"bypass" position. See Figures 7 & 8 on Page 7.
3. Slowly open the main water supply valve. Run
water until there is a steady flow from the opened
faucets, with no air bubbles.
4. Place bypass valve(s) in "service" or soft water
position as follows:
= Single bypass valve: Slowly move the valve stem
toward "service," pausing several times to allow
the water softener to fill with water.
= 3 valve bypass: Fully close the bypass valve and
open the outlet valve. Slowly open the inlet
valve, pausing several times to allow the water
softener to fill with water.
5. After about three minutes, open a hot water faucet
until there is a steady flow and there are no air
bubbles, then close this faucet.
6. Close all cold water faucets and check for leaks at
the plumbing connections that you made.
7. Check for leaks around clips at softener's inlet and
outlet. If a leak occurs at a clip, depressurize the
plumbing (turn off the water supply and open
faucets) before removing the clip. When removing
clips at the softener's inlet or outlet, push the single
bypass valve body toward the softener (See Figure
14). Improper removal may damage clips. Do not
reinstall damaged clips.
If removing
clips...
10
...depressurize the
plumbing, then push
Bypass Valve body
toward softener
FIG. 14

Advertisement

Table of Contents
loading

This manual is also suitable for:

Le18

Table of Contents