Verify Normal States
The Controller display and LEDs on Converters, shelf Alarm Cards, and Fan Shelves will illuminate when
power is applied to the system.
Step
Action
1.
2.
3.
1.
Follow the Troubleshooting section to resolve any alarm states
Verify UL Installation Compliance
Complete the final step to verify UL installation compliance.
Step
Action
Test each circuit by powering an open circuit at the remote end of the wire with a QS982 output. If red lights do not
flash, there is no leakage path to ground at operating voltage. If the FLT light does not blink yellow, there is no hard
short between tip and ring.
1.
Note: Circuit powering is usually accomplished by closing the circuit using a 5-pin protector with DC power applied to
the system.
Configure Controller
Refer to Galaxy Pulsar Edge Quick Start Guide.
Verify and edit controller parameters per site engineering instructions.
Basic Configuration:
Installation Tab:
Site ID, Site Description, System Date, System Time, and Shelf J-Code or Product Code
Network page (Settings tab, Communications group):
DHCP Client / Fixed IP Address
FTTN page (Settings tab, System group):
Alarm parameters
Page 28
© Copyright 2021 ABB. All rights reserved.