Procedure: ANNUAL INSPECTION INSTRUCTIONS
SERVICE
BULLETIN
3.2.4
Gyro Enclosure / Foundation –
Inspect enclosure, foundation frame, and hardware for corrosion and areas where paint should
be reapplied. Any loose paint should be removed and cleaned back to bare metal and
appropriate primer and top-coat paint system applied to seal the bare metal. See Service
Bulletin 90026 for paint information.
Inspect all eight retainer screws ( 2 per isolation mount )shown below and confirm all are tight
and safety retaining wire is in place.
Document #:
Rev:
90133
1
RETAINING SCREWS
2 PER ISOLATION MOUNT
ISOLATION MOUNT