5. INSTALLATION OF THE MACHINE

5.1 Preparation

5.1.1 The machine size and weight measurements, given the technical specification sheet.The ground, where the
machine will be placed, should be even, solid enough to bear the weight of the machine.
5.1.2 Please open the wooden package and get out the parts attentively.
5.1.3 Firstly doing montage of foot group (FIGURE 1-2 NO.34,39,81,82)
5.1.4 Connect the panel group as figure. (FIGURE 2 NO.95)
5.1.5 To connect the conveyor to machine you have requested,use the output flange plate (Figure 2.NO.41). To
adjust the height and uniformity of conveyor,please use the bolts on conveyor's foot (Figure 1 NO.81) and feet
of table. (Figure 1 NO.39)