Note: Refer to Appendix B (split-phase 120/240) or Appendix C (three phase 120/208) at the end of this manual
for the following instruction:
3
Terminate the loose end of the trunk cable in an AC junction box rated for use and installed as per the
local electrical code.
Branch
circuit to
distribution
panel

5.7 Installation: mounting the microinverter

1
Mark the approximate center of each panel / panel cluster on the frame.
2
Fix the screw(s) on the rail.
3
Hang the microinverter on the screw (see picture below), and tighten the screw(s).The silver cover side of the
Microinverter should be facing the panel.