2. Adjust the "Atom Air" control knob on the panel
until there is 50 psi flowing on the atom air gauge.
Check that the atom air pressure test gauge
shows a pressure.
1 00
1 00
3. Adjust the "Manual Fan Air" control knob on
the panel until there is 50 psi flowing on the fan
air gauge. Check that the fan air pressure test
gauge shows a pressure.
1 00
1 00
4. Turn the "Bell/Applicator" switch to "OFF"
position.
LN-9259-07.1
> Always verifty the flow meter regulator
is set at 100 psi.
5. Turn off the "Fan and Atom Air" controls.
6. Remove the test cap from the applicator.
S.A.I./ATOM
Flow Test
1. Turn on the "Water/Air" switch to the "Water"
position.
2. Turn on the pressure pot valve.
3. Turn on the"Paint Fluid Enable" switch.
S.A.O./FAN
4. Turn on the "Dump Trigger" until there is no air
in the line, then turn off.
Test Stations - Operation