Reports; Final Work Steps - Siemens POLYMOBIL Plus Start-Up Instructions

Hide thumbs Also See for POLYMOBIL Plus:
Table of Contents

Advertisement

4 - 2
The system must be switched on during the measurement. Measuring instruments with
automated measuring sequence must therefore be set to manual measurement.
Enter the highest value as first measured value in the report 'Device leakage current /
report' (Chapter 6 of these instructions).
This value must not exceed the permissible leakage current values according to DIN
VDE 0751-1:2001-10, Table F.1, line "Device leakage current for devices according to
the remarks 1 and 3", of 2.5 mA.
Transfer the current line voltage from the 'Start-up report' into the report 'Device leakage
current / report'. If the current line voltage deviates from the nominal voltage, correct the
measured value to the value that corresponds to a measurement at the nominal value of
the line voltage.
Also document the measuring method (differential measurement or direct
measurement) and the measuring instrument used (designation and serial number).

Reports

Separate the fully completed 'Start-up report' (Chapter 5 of these instructions) from
these instructions and file it in the system folder "Certificates" register.
Separate the completed reports 'Protective conductor resistance/ report' and 'Device
leakage current/ report' (Chapter 6 of these instructions) from these instructions and file
them in the system folder, "Certificates" register.
Complete the 'Installation Protocol' located on the system and send it to the address
stated in the protocol (by FAX).

Final work steps

Roll up the power line cable on the cable holder in back of the control console.
Move the support arm (Fig. 1) into the travel position and check the locking mechanism.
POLYMOBIL Plus
SPR8-125.034.02
Rev. 02
03.05
Final procedures