9 Finishing the outdoor unit installation

9.1 To finish the outdoor unit installation

9.2 To close the outdoor unit

(A)RXF20~42C5V1B
R32 split series
4P519439-10J – 2021.06
NOTICE
It is recommended that the refrigerant piping between indoor and outdoor unit is
installed in a ducting or the refrigerant piping is wrapped with finishing tape.
1 Insulate and fix the refrigerant piping and cables as follows:
d
c
a
b
g
a Gas pipe
b Gas pipe insulation
c Interconnection cable
d Field wiring (if applicable)
e Liquid pipe
f Liquid pipe insulation
g Finishing tape
2 Install the service cover.
NOTICE
When closing the outdoor unit cover, make sure that the tightening torque does NOT
exceed 1.3 N•m.
9
Finishing the outdoor unit installation
|
e
f
1
1
2
Installer reference guide
47

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents