SolarEdge UL1741-SA Installation Manual page 20

Single phase inverter with hdwave technology with setapp configuration
Table of Contents

Advertisement

Chapter 2: Installing the Power Optimizers
19
If connecting more modules than power optimizer inputs in parallel, use a branch
cable. Some commercial power optimizer models have a dual input.
Position the power optimizer close enough to its module so that their cables can be
connected.
Make sure to use power optimizers that have the required output conductor length.
Completely shaded modules may cause their power optimizers to temporarily shut
down. This will not affect the performance of the other power optimizers in the
string, as long as the minimum number of unshaded power optimizers connected in
a string of modules is met. If under typical conditions fewer than the minimum
power optimizers are connected to unshaded modules, add more power optimizers
to the string.
Equipment grounding tightening torques: 4-6 AWG: 45 lb-in, 8 AWG: 40 lb-in, 10-14
AWG: 35 lb-in.
To allow for heat dissipation, maintain clearance as specified below.
Figure 4: Power optimizer clearance
When installing modules in a confined space, for example, if installing Building-
integrated photovoltaic (BIPV) modules, ventilation measures may be needed to
ensure the power optimizers are not be exposed to temperatures outside their
specifications.
Single Phase Inverter with HD-Wave Technology Installation MAN-01-00541-1.4

Advertisement

Table of Contents
loading

Table of Contents