9 Test Run

• Before performing a test run, verify that the group setting has been performed and the startup sequence for the interlocked
operation setting has been completed.
• It may take approximately 5 minutes from power on until the local remote controller becomes operable.
Test run procedure
1 Turn the AG-150A and all air conditioning units on.
2 Set the "Test run" to [In use] on the Unit info on the Initial settings screen. After the setting is completed, the [Test run] button will
appear on the Operation screen.
3 Select the group to be tested on the Monitor/Operation screen and run the test.
4 Check for proper operation of each air conditioning unit during test run (e.g., check to see if cold (or warm) air comes out of the
supply air outlet on each indoor unit)
5 After confirming that all units are operating properly, stop the units either from AG-150A or from the remote controllers.
* Please refer to the Installation Manual that came with the indoor unit for further details on the test run method.