Cabling Verification; Turn-Up And Testing; Troubleshooting - ADC FRE-765 Manual

Remote terminal enclosure
Table of Contents

Advertisement

Functional Description

Cabling Verification

Verify the following connections:
Perform the following verifications before inserting any cards in the COT shelf.
1
Visually ensure that the ground wire is tightly secured to the grounding lug inside the FRE-765 and at the
ground termination point.
2
Visually verify that the HDSL lines are terminated properly and with the correct orientation. If the HDSL
lines are not connected properly, the COT will not communicate with the FRE-765.
3
Verify that the HDSL lines are "dry."
a
Verify 0 Vdc between the Tip and Ring, Tip and ground, and Ring and ground of each of the HDSL pairs
terminated at the FRE-765.
b
Verify a value greater than 100 kΩ resistance between Tip and ground, and Ring and ground for each of
the HDSL pairs terminated at the FRE-765.

Turn-Up and Testing

Refer to the COT Line Unit Technical Practice or RT Line Unit Technical Practice for complete COT and RT
turn-up and testing procedures.

Troubleshooting

Refer to the COT Line Unit Technical Practice or RT Line Unit Technical Practice for complete COT and RT
troubleshooting procedures.
14
January 6, 2003
SCP-FRE765-041-03H
FRE-765 List 4A

Advertisement

Table of Contents
loading

Table of Contents