Commissioning; Check Before Power-On - Huawei SUN2000 Series User Manual

Hide thumbs Also See for SUN2000 Series:
Table of Contents

Advertisement

SUN2000-(12KTL-25KTL)-M5 Series
User Manual

6.1 Check Before Power-On

Table 6-1 Installation checklist
No.
Check Item
1
SUN2000 installation
2
Smart Dongle
3
Cable layout
4
Cable tie
5
Grounding
6
Turn off the switches
7
Cable connections
8
Unused terminals and ports
9
Installation environment
Issue 01 (2022-06-15)
Copyright © Huawei Digital Power Technologies Co., Ltd.
6

Commissioning

Acceptance Criteria
The SUN2000 is installed correctly, securely, and
reliably.
The Smart Dongle is installed correctly and
securely.
Cables are routed properly as required by the
customer.
Cable ties are secured evenly and no burr exists.
The ground cable is connected correctly,
securely, and reliably.
The DC SWITCH and all the switches connected
to the SUN2000 are set to OFF.
The AC output power cable, DC input power
cable, and signal cable are connected correctly,
securely, and reliably.
Unused terminals and ports are locked by
watertight caps.
The installation space is proper, and the
installation environment is clean and tidy,
without foreign matter.