SUN2000-(12KTL-25KTL)-M5 Series
User Manual
8.1 Powering Off the System
Precautions
● After the system is powered off, the inverter is still energized and hot, which
● Power off the system before maintaining optimizers and PV strings. Otherwise,
Procedure
Step 1 Send a shutdown command on the app.
Step 2 Turn off the AC switch between the inverter and the power grid.
Step 3 Set DC SWITCH to OFF.
Step 4 (Optional) Install the locking screw next to DC SWITCH.
Step 5 Turn off the DC switch between the inverter and PV strings.
----End
8.2 Routine Maintenance
To ensure that the SUN2000 can operate properly for a long term, you are advised
to perform routine maintenance on it as described in this chapter.
Issue 01 (2022-06-15)
WARNING
may cause electric shocks or burns. Therefore, wait for 5 minutes after power-
off and then put on protective gloves to operate the inverter.
electric shocks may occur when the PV strings are energized.
Copyright © Huawei Digital Power Technologies Co., Ltd.
8
Maintenance
8 Maintenance
56