Site And Installation Planning; Requirements - Emerson AXP640-DC2 Installation & Use Manual

Table of Contents

Advertisement

8. Tighten loose screws before proceeding.
9. Remove the desiccant bags delivered together with the system and dispose of
them according to your country's legislation.
The system is thoroughly inspected before shipment. If any damage occurred during
transportation or any items are missing, please contact our customer's service immediately.
3.2.2

Site and Installation Planning

Planning basic site and installation requirements you have to consider the following issues:
Adequate power should be available for the AXP640 system.
For AC, the system should be positioned in a way that 100 VAC to 240 VAC power source
is easy to reach.
For DC, the system should be positioned in a way that -48 VDC to -60 VDC power source is
easy to reach.
There should be sufficient space in racks to install the system.
Suitable equipment should be available to lift the system into the rack.
There should be unrestricted area for inlet and outlet of the fans and therefore the airflow
is not blocked.
For Installation in restricted access location.
For use by trained personnel.
3.2.3

Requirements

Before and during system installation and operation, you always have to ensure that the
requirements listed in the following sections are met.
AXP640 Installation and Use (6806800M24E)
Site Preparation
55