required; writing the information back to the devices;
and re-reading the device data.
4. With no map errors displayed, put an input device on
the circuit in the active mode. Verify the appropriate
message is displayed on the LCD module and
graphic annunciator, where installed. Put the input
device in the trouble mode and verify that the correct
trouble message is displayed.
Initial acceptance testing for LED displays, VM-1
SCS panels, and FSCS series graphic annunciators
1. Verify that the displays are properly installed on the
SCS panel module and in the graphic annunciator
panel. Verify that the ribbon cable between the
display and its host module is firmly seated on both
ends.
2. For the SCS panel perform a lamp test: Main Menu
> Test > Lamp Test.
For the graphic annunciator panel press the
momentary button.
Initial acceptance testing for control/LED displays,
VM-1 SCS panels, and FSCS series graphic
annunciators
1. Verify that the displays are properly installed on the
SCS panel module or graphic annunciator panel.
Verify that the ribbon cable between the display and
its host module is firmly seated on both ends.
2. For the SCS panel perform a lamp test: Main Menu
> Test > Lamp Test.
For the graphic annunciator panel press the Lamp
Test button.
3. Perform a functional button test.
VM-1 SCS detection
acceptance testing
The procedures listed in this section should be
performed on the detectors, input modules, output
modules, and related accessories connected to each
cabinet. Additional procedures for manual initiating
devices may be found in "Smoke control input modules"
on page 58. These procedures are presented to test the
devices and smoke control system programming.
VM-1 Smoke Management Application Guide
Chapter 4: Smoke control acceptance and testing
Note:
The network configuration, control module
information must be downloaded into the network and
the audio controller, using the software configuration
utility, before testing begins.
Every detector connected to the smoke control system
should be visited, and manually activated during the
installation process to verify that:
The location meets design parameters for spacing
and air flow.
The location annunciated by the smoke control
system agrees with the physical location of the
device.
That the activated device initiates the correct smoke
control system response.
Initial acceptance testing for V-Series and Signature
Series detectors and bases
1. Verify that all components are installed in a
workman like manner.
2. Individually activate each detector. Verify that the
appropriate alarm and location message is displayed
on the LCD module. Verify that the detector initiates
the appropriate system responses. If the detector is
installed in a relay base, verify that the base's relay
function operates correctly. If the detector is installed
in an isolator base, verify that the base isolates the
required circuit segments.
3. Duct mounted detectors should be tested to verify
that minimum and maximum airflow requirements
are met and that smoke control actions or overrides
are functioning.
4. Remove the detector from its base. Verify that the
appropriate trouble and location message is
displayed on the LCD module.
5. After all detectors have been individually inspected,
run a Sensitivity report, using the Reports command.
Initial acceptance testing for conventional smoke
detectors on a GSA-UM(-MAB)
1. Verify that all components are installed in a
workmanlike manner.
2. Verify that jumper JP1 on each UM or MAB module
is installed across pins 1 and 2.