Commissioning and adjustment
Commissioning
In menu option "Commissioning" high-
light the required sub-option with "
or "
" and confirm with "select".
The following functions can be adjusted under menu option
"Commissioning":
Supply auger
The supply auger is started for 6 min.
Supply
The supply and every wand is started
with a purging program subject to the
selected supply system.
Actuator test
In menu option "Actuator test" high-
light the required sub-option with "
or "
" and confirm with "select".
Note
The functions are respectively started
for 1 min. The control unit carries out
a self-test following the termination of
the actuator test.
8
"
The following functions can be con-
"
trolled:
Induced draught fan
Supply auger
Grate shaking
Ignition element
Ash removal
Heating surface cleaner
Suction turbine
Wand changeover
Ventilation/extract air damper