Commissioning; Check Before Startup - Gree GRS-Cm18PdRe/NhA-M Owner's Manual

Air-to-water heat pump
Table of Contents

Advertisement

GRS-Cm18PdRe/NhA-M

12 Commissioning

12.1 Check before startup

For safety of users and unit, the unit must be started up for check before debugging. The
procedures are as below:
The following items shall be performed by qualified repair persons.
Confirm together with the sales engineer, dealer, installing contractor and customers for the following items finished or tobe
finished.
No.
If the contents of Application for Installation of this Unit by Installer are real. If not, debugging will be
1
refused.
2
Is there written notice in which amendment items are shown in respect of unqualified installation?
3
Are Application for Installation and Debugging list filed together?
No.
1
Is appearance of the unit and internal pipeline system ok during conveying, carrying or installation?
2
Check the accessories attached with the unit for quantity, package and so on.
3
Make sure there is drawings in terms of electricity, control, design of pipeline and so on.
4
Check if installation of the unit is stable enough and there is enough space for operation and repair.
5
Completely test refrigerant pressure of each unit and perform leakage detection of the unit.
Confirmation of Installation
Pre-check
24
Air-to-water Heat Pump

Advertisement

Table of Contents
loading

Table of Contents