1. Measure the DC voltage
between the output
terminals of the charge post:
Use the voltage tester.
2. Make sure that all the
measured voltages are 0 V.
4.5

Maintenance and cleaning

4.5.1

Maintenance schedule

Task
Do a check for damage on the
EV charge cables and the con-
nectors.
Do a check of the safety stickers
for damage.
Clean the power cabinet.
Clean the charge post.
Do a check for damage on the
power cabinet.
Do a check for damage on the
charge post.
Make sure that the manufactur-
er does maintenance on the
EVSE.
30
Voltage tester
A + to A-
A+ to ground
A- to ground
A+
Frequency
Procedure
3 months
Refer to section 4.5.4.
3 months
Do a visual check on the reada-
bility and presence of the safety
stickers.
If a safety sticker has damage,
replace the safety sticker. Refer
to sections
4 months
Refer to section 4.5.2.
4 months
Refer to section 4.5.2.
6 months
Refer to section 4.5.3.
6 months
Refer to section 4.5.4.
1 year
Ask the manufacturer to do the
task. Refer to section 1.12.
For the complete maintenance
schedule refer to section 7.11.
A-
4.5.5
and 4.5.6.
9AKK107992A3070-EN | 003

Advertisement

Table of Contents
loading

Table of Contents