Packing List The following items are included: XL Preheater Unit ........1 unit XL PCB Support ........1 unit Ref. PHXL-SA Console ......1 unit Metallic Supports for PCB RJ45 Cable ....1 unit Ref. ACE-A Ref. PH201....4 units Ref.
w w w.jbctools.com Features and Connections Heater Unit Heating Areas Fixing brackets for Zone A Zone B Thermocouple XL PCB Support Connectors x8 (Type K) For Electrical Power Supply RJ45 Connector Connection to Console Main Switch RJ12 Connector to Robot USB-B Connector Pedal Connector Button for Foot...
Page 4
Connection to Power Supply RJ45 Cable Ref. 0019914 Connection to Power Supply PHXLE-KA can be connected to single-phase or three-phase networks. A power supply cable is required. Use the following table to determine the cable size and connection: Peak Current Cable Connection Wire Section Single-phase Three-phase...
Page 5
E 1:1 w w w.jbctools.com To conect your power supply cable to the Heater Unit do as follows: MONOPHASIC TRIPHASIC (100V to 230V) (173V to 400V) Cable grommet 1. Unscrew the four screws and remove the 2. Insert the cable through the cable grommet cover.
Height Adjustment PHXL-SA allows adjustment to 3 heights between the PCB and the heating area of the Preheater. Select the adequate PH201, PH202, PH203 for your working level. Arrange the selected supports between the PCB and the Preheater to stabilize the PCB so as to avoid PCB deformatiion. Low level 28 mm Ref.
Page 7
w w w.jbctools.com Fast PCB Replacement The support lets you replace PCBs of the same batch fast and easily. Use the sliding guides to change the PCBs. Removing the PCB Loosen one sliding guide, pull back and lift out the PCB. Sliding Guide Sliding Guide Knobs Placing another PCB...
Page 8
Work Screen The Console offers an intuitive user interface which provides quick access to station parameters. 14:15 Status Bar 14:15 º Status Indicator Instant Power Selected 120 º º TC1 Current Supplied to and Selected Heater Temperature º Selected 120 º...
Page 9
w w w.jbctools.com Setting Thermocouples Function Select Thermocouples from the Work mode menu to set them up. The thermocouples (TC) can work in three diferent ways depending on what is needed. · Control: the unit mantains the selected temperature. · Protection: the Heater Unit stops if the TC reaches the selected temperature. ·...
Page 10
Work Mode Temperature Mode Select Temp. mode from the Work mode menu. In this mode the heater unit maintains the selected temperature for the TC1 thermocouple as long as the other TC’s do not reach the control/protection temperature limit. Status Bar 14:15 Status Indicator...
Page 11
w w w.jbctools.com Profile Modes Select Profile Mode from the Work Mode Menu. In this mode the heater unit regulates the temperature of the TC1 thermocouple according to the selected profile as long as the other TCs do not reach the control/protection temperature limit. 14:15 PROFILE1 Stop...
Page 12
JBC Set Profiles There are 3 profiles predefined by JBC: A, B and C. The difference between them is the number of steps: 2, 3 or 4. The thicker your PCB is and the more layers it contains, the more steps are needed to obtain a gradual warming.
Page 13
w w w.jbctools.com Process Analysis By pressing Graphics in the main MENU, temperature of TC1 thermocouple and power fi gures in real time are displayed. Graphics 14:15 Power (%) Temperature (ºC) Power [%] Ext. Temp [ºC] Switch Y Axis Between Power and Temperature System Notifications The following icons will be displayed on the screen’s status bar.
Page 14
Insert a USB flash drive into the USB-A connector to export / import profiles. Update the Station Software 1. Download the JBC Update File from 2. Insert the USB flash drive to the console. www.jbctools.com/software.html and save The icon is diplayed while updating.
Page 15
- Only if it is absolutely necessary and if cleaning with isopropyl alcohol (IPA) is not enough, it is recommended to use a scraper to remove dirt in the glass area. - Replace any defective or damaged parts. Use original JBC spare parts only. - Repairs should only be performed by a JBC authorized technical service.
Page 16
Safety It is imperative to follow safety guidelines to prevent electric shock, injury, fire or explosion. - Do not use the units for any purpose other than PCB preheating. Incorrect use may cause fire. - The mains cable must be plugged into approved bases. Make sure that it is properly grounded before use.
w w w.jbctools.com Specifications XL Preheater Set PHXLE-1KA 120V. Input 120V 50/60Hz Fuse T20A PHXLE-2KA 230V. Input 230V 50/60Hz Fuse T10A PHXLE-9KA 100V. Input 100V 50/60Hz Fuse T20A XL Preheater Unit - Maximum Power: 5400W - Heating Area (L x W): Zone A 510 x 200 mm / 20 x 7.9 in Zone B...
Page 20
In order for the warranty to be valid, equipment must be returned, postage paid, to the dealer where it was purchased. Get 1 extra year JBC warranty by registering here: https://www.jbctools.com/productregistration/ within 30 days of purchase. This product should not be thrown in the garbage.
Need help?
Do you have a question about the PHXLE-K and is the answer not in the manual?
Questions and answers