2) Installation of device

4. Space for installation

●Control unit
●Power unit
●LED head
Do not install the control unit, power unit, and LED head in a sealed space.
Please have a margin to installation space, and do not allow the exhaust air from the fan to enter through the air intake.
Perform installation of LED head to customer's equipment securely using total of 8 pieces of M4 screws on the side
faces of the head. (Standard tightening torque: 1.0N·m)
See the LED head specification sheet for details on LED head installation needed for appropriate installation.
- 20 -