7 Commissioning

If
≥1 MΩ
Insulation resistance is OK. This procedure
is finished.
<1 MΩ
Insulation resistance is not OK. Go to the
next step.
2 Turn ON the power and leave it on for 6 hours.
Result: The compressor will heat up and evaporate any
refrigerant in the compressor.
3 Measure the insulation resistance again.
7
Commissioning
NOTICE
General
commissioning
commissioning instructions in this chapter, a general
commissioning checklist is also available on the Daikin
Business Portal (authentication required).
The general commissioning checklist is complementary to
the instructions in this chapter and can be used as a
guideline and reporting template during the commissioning
and hand-over to the user.
7.1

Overview: Commissioning

This chapter describes what you have to do and know to
commission the system after it is installed.
Typical workflow
Commissioning typically consists of the following stages:
1
Checking the "Checklist before commissioning".
2
Performing a test run for the system.
7.2

Precautions when commissioning

INFORMATION
During the first running period of the unit, the required
power may be higher than stated on the nameplate of the
unit. This phenomenon is caused by the compressor, that
needs a continuous run time of 50  hours before reaching
smooth operation and stable power consumption.
NOTICE
Before starting up the system, the unit MUST be energised
for at least 6  hours. The crankcase heater needs to heat
up the compressor oil to avoid oil shortage and
compressor breakdown during startup.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure
sensors/switches. If NOT, burning of the compressor might
be the result.
NOTICE
ALWAYS complete the refrigerant piping of the unit before
operating. If NOT, the compressor will break.
NOTICE
Cooling operation mode. Perform the test run in cooling
operation mode so that stop valves failing to open can be
detected. Even if the user interface was set to heating
operation mode, the unit will run in cooling operation mode
during 2‑3 minutes (although the user interface will display
the heating icon), and then automatically switch to heating
operation mode.
Installer reference guide
26
Then
checklist.
Next
to
the
NOTICE
If you cannot operate the unit in test run, see
codes when performing a test
WARNING
If the panels on the indoor units are not installed yet, make
sure to power OFF the system after finishing the test run.
To do so, turn OFF operation via the user interface. Do
NOT stop operation by turning OFF the circuit breakers.
7.3

Checklist before commissioning

After the installation of the unit, first check the items listed below.
Once all checks are fulfilled, the unit must be closed. Power-up the
unit after it is closed.
You read the complete installation instructions, as
described in the installer reference guide.
The indoor units are properly mounted.
In case a wireless user interface is used: The indoor unit
decoration panel with infrared receiver is installed.
The outdoor unit is properly mounted.
The following field wiring has been carried out according
to this document and the applicable legislation:
▪ Between the local supply panel and the outdoor unit
▪ Between the outdoor unit and the indoor unit (master)
▪ Between the indoor units
There are NO missing phases or reversed phases.
The system is properly earthed and the earth terminals
are tightened.
The fuses or locally installed protection devices are
installed according to this document, and have NOT been
bypassed.
The power supply voltage matches the voltage on the
identification label of the unit.
There are NO loose connections or damaged electrical
components in the switch box.
The insulation resistance of the compressor is OK.
There are NO damaged components or squeezed
pipes on the inside of the indoor and outdoor units.
There are NO refrigerant leaks.
The correct pipe size is installed and the pipes are
properly insulated.
The stop valves (gas and liquid) on the outdoor unit are
fully open.
7.4

To perform a test run

This task is only applicable when using the BRC1E52 or BRC1E53
user interface. When using any other user interface, see the
installation manual or service manual of the user interface.
NOTICE
Do not interrupt the test run.
INFORMATION
Backlight. To perform an ON/OFF action on the user
interface, the backlight does not need to be lit. For any
other action, it needs to be lit first. The backlight is lit for
±30 seconds when you press a button.
"7.5  Error
run" [ 4  27].
RZA200+250D7Y1B
Sky Air Advance-series
4P573383-1 – 2019.04

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sky air advance rza200d7y1bSky air advance rza250d7y1b

Table of Contents