5.2.6
Setting down the machine
Requirements
The following preconditions must be satisfied before setting down the machine at the
installation location:
● The mating faces must be clean.
● The anti-corrosion protection paint has been removed from the mating faces, such as the
Setting down the machine
Set down the machine slowly and carefully at the installation location to avoid any impact.
5.2.7
Roughly aligning the machine
Requirement
The transmission element such as a coupling half has already been pulled on.
Roughly aligning the machine
● For horizontal positioning, push the motor sideways across the foundation. When doing so,
5.3
Installing the machine
5.3.1
Preconditions for smooth, vibration-free operation
Preconditions for smooth, vibration-free operation:
● Stable foundation design as per DIN 4024
● Precise alignment of the machine
● Correct balancing of parts to be fitted to the shaft end.
● Maintaining the vibration velocity according to ISO 10816-3
LOHER CHEMSTAR 1PS5
Operating Instructions 03/2014
machine mounting feet, flange, ...
ensure that the axial position is maintained.
Assembling
5.3 Installing the machine
49