Pump Down Operation

1. Pump Down Operation

Pump Down
In order to protect the environment, be sure to conduct pump down operation when relocating or
disposing of the unit.
Operation
1. Remove the valve caps from the liquid stop valve and the gas stop valve.
2. Carry out forced cooling operation.
3. After 5 ~ 10 minutes, close the liquid stop valve with a hexagonal wrench.
4. After 2 ~ 3 minutes, close the gas stop valve and stop the forced cooling operation.
202
Gas stop valve
Liquid stop valve
Close
Hexagonal wrench
Valve caps