Viessmann Vitomax LW Operating And Service Instructions page 12

Low pressure hot water boiler
Hide thumbs Also See for Vitomax LW:
Table of Contents

Advertisement

Commissioning
Commissioning
Note
When commissioning, ensure that the installation room
is well ventilated, as unpleasant odours may occur.
Authorised to commission the boiler:
Viessmann Industrial Service (for contact details, see
page 33) or
The system installer or
An approved contractor or institution nominated by
the system installer
Commissioning after boiler idle periods, cold starts
Cold start to EN 12953-3
Boiler start-up from ambient pressure at room temper-
ature to normal operation (full pressure cycle)
See engineering information for boiler cold/warm
start
!
Please note
A start-up report must be filled in for each cold
start. For start-up reports, see page 34.
Start-up reports are a prerequisite for verifying
the warranty.
12
During commissioning, country-specific require-
ments must be observed, e.g.:
Presence of a competent expert authority
Preparation of all necessary test reports; see 34
Required signatories:
System installer
Official expert authority
System user
The flue gas inspector (where applicable) should be
notified of commissioning within 4 weeks
!
Please note
Prevent unnecessarily high mechanical stress
and condensate formation in the flue gas during
a cold start. Wait until the boiler has reached
normal operating conditions before slowly heat-
ing up the consumer network.