IBM Power775 Service Procedure page 43

Disk enclosure rails service procedure
Hide thumbs Also See for Power775:
Table of Contents

Advertisement

Power775 Disk Enclosure Rail Service Procedure
STEP 38
Grasping the blue-purple recessed touch points on the front DE cable tray, pull the DE out of the frame a few
inches until the front cable tray is just above the first Lift Tool roller (see Figure 41).
STEP 39
Raise the Lift Tool until the roller contacts the DE.
Using the Manual Drive raise the lift tool table so it contacts the DE and then slightly further to transfer the
DE weight to the lift tool table. Do not raise the lift tool table too high as this will result in the DE being
driven into the CEC or BPA above which can cause damage (see
Figure 40 Cable protector sheet shown in upper left position
Figure 41 Blue-purple Recessed Touch Points
43 of 57
Figure 42
).