Installing The Duct; Electric Wiring Work - Daikin FXDQ-SPV1 Engineering Data

Table of Contents

Advertisement

FXDQ-SPV1
(2) When the pipe work is completed, please check
whether the water drainage is smooth.
Case for Model FXDQ ~ SPV1
CAUTION
·
The electrical wiring work shall be carried out by
qualified professional electricians.
·
When the professional electrician is not on site,
please follow Step 3 ~ 7 after the system test run is
completed to carry out drainage to confirm that it works.
1. Remove the electrical box cover, and then connect
the remote control cable and the power cable
(Power supply: Single phase, 50 Hz, 220-240 V)
to their corresponding terminal block. Also connect
the grounding cable. (Refer to the below figure)
CAUTION
To prevent the wiring connection from being pulled
by extra tension, please follow the methods as
shown in Fig. 14 to fix firmly with banding tie (9)
and (10).
2. Before switching on the power supply, please
confirm whether the electrical box cover has been
completely covered.
3. Please remove the repair cover.
4. Slowly fill about 1000 cc water into the water
drainage pan from the repair opening, so as to
check the water drainage situations.
CAUTION
Please never apply any external force to the
floating valve switch.
(Otherwise error can occur.)
5. Please install the repair cover.
6. Please carry out the following operations for the
remote control so as to check the water drainage
situations.
·
Press the observation / test run button "
the remote control. The air conditioner will enter
into the test run mode. Press the run mode select
button "
", and select the air supply "
·
Press the ON/OFF button "
water drainage pump of the indoor unit start to run.)
CAUTION
Please note that the fan is also running at this time.
Please never touch the water drainage pump to
prevent any electrical shock.
Water
drainage port
Repair opening
Manual pump
Refrigerant
pipe
Water drainage
port for repair
Water barrel
PCB assy for the indoor unit
P1
P2
F1
F2
T1
T2
REMOTE
TRANSMISSION
FORCED
CONTROL
WIRING
OFF
Wiring method for the
remote control terminal
7. Please always use the remote control to switch off
to stop water drainage and confirm that it works.
8
" on
TEST
".
". (The fan and
Repair cover
L
N
L N
Power supply,
P1
P2
F1
F2
T1
T2
REMOTE
TRANSMISSION
FORCED
single phase
CONTROL
WIRING
OFF
1~ 220-240 V,
50 Hz Wiring
method for the
power supply
terminal
Terminal block
Terminal block

8. INSTALLING THE DUCT

Please connect the air pipe supplied on site.
Air inlet side
·
Please install the flange on the air supply side
(supplied on site).
·
Please use the supplied bolt (7) to connect the flange
and the main body of the air conditioner.
(Point 12, 14 or 16)
·
Use sealing materials such as aluminum adhesive tape to
seal the connection section between the flange and the
air pipe on the air inlet side, so as to prevent air leakage.
CAUTION
·
Always install the air filter element in the air channel in
the air inlet side. (Always select one air filter with the
dust collecting efficiency of over 50% (by weight).)
Flange
(Supplied on site)
Main body
of the
Bolt for connection (7)
air conditioner
(Accessory)
Aluminum adhesive tape
(Supplied on site)
Air supply side
Air outlet side
·
Connect the air pipe to the inside of the flange in the
air supply side.
·
Use sealing materials such as aluminum adhesive
tape to seal the connection section between the flange
and the air pipe on the air outlet side, so as to prevent
air leakage.
CAUTION
·
Always use heat insulation material to prevent condensate
on the air pipe. (Material: Glass wool or foamed
polyethylene, thickness: 25 mm).
·
In case that the metal air pipe passes any metal wire,
metal wire net or metal plate of any wood structure, ensure
that the air pipe and the wall are (electrically) insulated.
·
Please instruct the operating methods and cleaning
methods of the parts supplied on site to the user (air filter,
grille (suction inlet and blow outlet), etc.).

9. ELECTRIC WIRING WORK

9-1 General
·
Before carrying out any electrical work, always switch
off the power supply.
·
Any part and material locally purchased as well as any
electrical work shall comply with the local regulations.
·
Always use copper cables.
·
When carrying out electrical wiring work, please also
refer to the "Wiring Diagram" attached to the electrical
box cover.
·
For details on the wiring of the remote control, please
refer to the "Installation instruction manual for remote
control" supplied with the remote control.
·
Any wiring work shall be carried out by qualified
professional electricians.
·
The system consists of many indoor units. Please name
the individual indoor units as Unit A, Unit B, ..., and
confirm whether the cables connecting from the terminal
board to the outdoor unit and the BS device match
accordingly. In case that any connection of the cables
or pipes between the outdoor unit and the indoor unit
is incorrect, the air conditioning system will not work
normally. To prevent any error, please refer to
[Wiring Examples] for wiring.
·
Wire circuit breaker or electricity leakage circuit breaker
must be installed in the power supply point.
·
The grounding resistance must be below 4 Ω.
33
EDTFVN391825
Heat insulation material
Flange
(Supplied on site)
Aluminum adhesive tape
(Supplied on site)
Air outlet side
3P347455-11H