Connecting The Gas Pipes - Siemens 3AP2-FI Operation & Maintenance Manual

400kv
Table of Contents

Advertisement

4 Installation
15.9
10.1
10.9
18.27.1
1
Marking position
2
Operation position
10.1
Bolt with lock washer
10.9
Bolt
15.9
Lever
18.27.1
Driving rod
Fig. 49
Coupling the operating mechanism
Set up the two other poles in the same way replacing the original screws after removal of the lifting eye-bolts.
Next pull the bolt 10.9 out at all three poles (Fig. 49) so that it can be secured in the ring groove with the locking
plate 10.1 and two M6 screws.
Bend the locking plate after tightening the two M6 screws.
4.5.11

Connecting the Gas Pipes

During assembly of the tube connections, ensure that the sealing surfaces are clean and the O-ring gasket is in
perfect condition.
An gas line must be connected for each pole column.
10.1
10.9
66