10

Check after installation and test operation

10.1 Check after installation

• E lectrical safety Check
1. If the supply voltage is as required.
2. If there is any faulty or miss connection in each of the power, signal and grounding wires.
3. If the grounding wire of the air conditioner is securely grounded.
• I nstallation safety Check
1. If the installation is secure.
2. If the water drain is smooth.
3. If the wiring and piping are correctly installed.
4. Check that no foreign matter or tools are left inside the unit.
5. Check the refrigerant pipeline is protected well.
• L eak test of the refrigerant
Depending on the installation method, the following methods may be used to check for suspect leak,
on areas such as the four connections of the outdoor unit and the cores of the cut-off valves and
t-valves:
1. Bubble method: Apply of spray a uniform layer of soap water over the suspected leak spot and
observe carefully for bubble.
2. Instrument method: Checking for leak by pointing the probe of the leak detector according to the
instruction to the suspect points of leak.
C
Note: Make sure that the ventilation is good before checking.

10.2 Test operation

Test operation preparation:
• V erify that all piping and connection cables are well connected.
• C onfirm that the values at the gas side the liquid-side are fully open.
• C onnect the power cord to an independent power socket.
• I nstall batteries in remote control.
C
Note: Make sure that the ventilation is good before testing.