4.2

LAN cabling

Installation site should be prepared with gel outdoor CAT5e Ethernet LAN cable. Cable should be crimped
with RJ45 connector following Ethernet standard.
Required Ethernet cable length is 2 meters long.
o
Ethernet 2m
Cable should be prepared inside the footprint of the EV quick Charger. Check exact cable location in chapter
4.5.3
4.3

Load-management connection

Installation of the load-management equipment should be allowed in power meter room.
o
In close distance to power meter
o
Box size ~20x40x30cm (D x W x H)
o
AC power supply available
Cable connection distance between power meter room and EVC should not exceed 250m
4.4

Load-management cabling

Installation site should be prepared with outdoor CAT5e gel outdoor CAT5e cable. Required cable length is 2
meters long.
o
Ethernet 2m
Cable should be prepared inside the footprint of the EV quick Charger. Check exact cable location in chapter
4.5.3
Cable distance between power meter room and EVC should not exceed 250m