Electrical connections
NOTES
The electrical wirings must be carried out in conformity with the regulations in force in the countries of destination, and
by qualified personnel. Riello S.p.A. cannot accept any responsibility for modifications or connections other than those
shown in these diagrams.
Use flexible cables according to EN 60 335-1 Regulations:
• if in PVC sheath, use at least H05 VV-F;
• if in rubber sheath, use at least H05 RR-F.
All the wires to connect to the burner terminal strip 9)(A) must enter through the supplied fairleads.
The fairleads and hole press-outs can be used in various ways; the following lists show one possible solution:
D886
NOTES
• The RS 160/M BLU burner has been type- approved for intermittent operation. This means it shoulds compulsorily be stopped at least once
every 24 hours to enable the control box to perform checks of its own efficiency at start-up. Burner halts are normally provided for automati-
cally by the boiler load control system. If this is not the case, a time switch should be fitted in series to IN to provide for burner shut-down at
least once every 24 hours.
• The TR and TL load controls are not required when the RWF is connected, as their function is performed by the RWF itself.
MODULATING OPERATION
If the output power regulator kit RWF or the converter 0...10V / 4...20mA is connected, in 3-point signal, the thermostat/pressure TR must be
removed.
In addition, the function Q13 - Q14 of the regulator RWF can substitute the thermostat/pressure switch TL.
In this case, the thermostat/pressure switch TL connected to the X7 must be removed.
On the contrary, if you want to maintain the thermostat/pressure switch TL, it must be adjusted so as not to interfere with the working of the reg-
ulator RWF.
The thermal cutout k1 (RWF) can be connected to the terminals:
-
2 - 3, to replace the remote control TL;
-
AL - AL1, to control an alarm device.
ATTENZIONE:
- Do not invert the neutral with the phase in the electrical supply line. An inversion would lead to lockout due to ignition
failure.
- Replace the components only with original spare parts.

APPENDIX

RS 160/M BLU
1- Pg 13,5 Three-phase power supply
2- Pg 11
Single-phase power supply
3- Pg 11
Remote control device TL
4- Pg 9
Remote control device TR or probe RWF
5- Pg 13,5 Gas valves
6- Pg 13,5 Gas pressure switch or gas valve leak detection
control device
7- Pg 11
Open the hole, if a pipe union is to be added