2. Installation

Unpacking
Check the packaging for any signs of damage. Carefully remove the machine and retain the packaging
until the installation is complete.
Positioning of the machine
Place the Viper 2500s on a clean dry surface, preferable above ground level.
• Make sure there is at least 20cm clearance at the front and rear of the machine to allow good
circulation of the cooling air.
• Protect the machine from heavy rain and if used in hot climates, against direct sunlight.
• Ensure that the machine is positioned in such a way so that particles created by grinding and cutting
operations do not enter the machine.
Connecting welding cables
Only use copper welding cables with a cross sectional area of 35mm2 or more.
• Connect the negative (-ve) cable from the power source to the 'negative in' connector on the rear of the Viper.
• Connect the positive (+ve) cable from the power source to the 'positive in' connector on the rear of the Viper.
INVERTER POWER SOURCE
Connecting for MMA operation
• Connect the Electrode Holder to the positive out connector on the front of the Viper.
• Connect the Earth return lead to the negative out connector on the front of the Viper.
Note! When using a reverse polarity procedure, always swap the polarity of the output cables.
NEVER swap the polarity of the input cables.
Connecting for TIG operation (As shown above)
• Connect to the power gas adaptor to the negative output connector on the front of the Viper.
• Connect the gas pipe of the power gas adaptor to the quick release connector between the output terminals.
• Connect the TIG torch to the power gas adaptor.
• Connect the Earth return lead to the positive output connector on the front of the Viper.