Putting A Decommissioned Compressor Back Into Operation; Display Of The Compressor Controller - Gardner Denver L Series Original User And Service Manual

Frame 5 base mounted compressor
Hide thumbs Also See for L Series:
Table of Contents

Advertisement

8.2

Putting a decommissioned compressor back into operation

Before commissioning the compressor all the electrical and electronic components and units should be checked for the
ingress of water or condensation.
If the electronic control system was removed during shut down, it must be re-installed.
Then proceed as described in Section 8.1 'First commissioning'.
NOTICE
Only for L90RS-L132RS: If the compressor has been in storage for a substantial period of time (up to
2 years), switch the main power supply switch on (ON) at least one (1) hour prior to commissioning. This
ensures the operability of the capacitors and prevents any damage from occurring.
If the compressor has been in storage for longer than 2 years, please contact an authorized Gardner
Denver Distributor prior to start-up.
8.3

Display of the compressor controller

Fig. 15
1. Touchscreen Display
2. Start push-button [ I ]
3. Stop push-button [ O ]
4. Emergency stop
13-25-639 v00
Page 37