Operating Controls; Initial Set-Up - Bunn G9-2T DBC Installation And Operating Manual

Bunn g9-2t dbc: operating manual
Hide thumbs Also See for G9-2T DBC:
Table of Contents

Advertisement

d
a
e
Grind Pad (a)
Pressing the GRIND button initiates a timed grind cycle.
Stop Pad (b)
Pressing the STOP button ends the operation of the grinder.
® PAD (c)
Pressing the ® pad allows programming access (see page 6).
Hopper/Batch Selector Pads (d)
These pads are located on the funnel depictions on each side of the grinder with a total of 6 pads. Selecting
one of these pads will select the amount of grind and side from which to grind.
Example: Selecting the lower pad on the left side will grind enough beans from the left side of the grinder
to brew the amount programmed into grinder.
Power ON/OFF Pad (e) (100V Models)
Pressing the ON/OFF pad alternately turns the grinder on and off.
Control Board
The control board determines the amount of beans that will leave the hopper in a grind cycle. The timer por-
tion can be adjusted to dispense a different amount from each hopper and each batch size. The scale is from 0.4
to 99.9 seconds. Refer to the Adjustments section for timer setting chart (page 8).
1. Open the top lid. Clear all foreign objects and shipping material from the hopper compartment and the en-
trance to the grind chamber.
2. Plug in the grinder.
3. Fill the hopper compartments with whole bean coffee. (Capacity 6 pounds each). The grinder is now ready
for use.

OPERATING CONTROLS

c

INITIAL SET-UP

4
d
b