STEP 5-COMPLETING THE INSTALLATION

To complete the installation and system checkout requirements, the following steps must be
performed.
1.
Check the thermostat position. Make sure the thermostat is routed through the holding guide
and is not touching any metal surface.
2.
Make sure the guide louver and the filters are properly positioned in the ceiling grille.
3.
Secure the ceiling grille to the ceiling assembly frame with 4 screws. (see Figure 10).
4.
Install screw caps into four screw holes.
5.
Switch on the power supply and check the unit work or not.
4 Screws and 4 Screw cap
Copyright 2018. This translation is property of GREE PRODUCTS SL. All rights reserved. Total or partial reproduction without its express authorization is prohibited.
Figure 10
- 21 -
Frame
Ceiling Grille

Advertisement

Table of Contents
loading

This manual is also suitable for:

Grh120da-k3na1a

Table of Contents