Installation guidelines
4. After mating all locator plates in place with the
rails, secure the locator plates and the rails.
5. Position overhead lift device on the tines of
forklift. Raise the overhead lift device up to the
rails on the frame.

Raise lift device

Align wheels on the front rail and behind the rear
rail. Adjust the upper-rear wheel to minimize
vertical movement.

Align wheels

Push device off the forklift

Push the overhead lift device off the forklift onto
the rails.
Test the continuous movement of the overhead lift
device. If the movement is correct, reinstall the
carriage stop bracket.

Operating the overhead lifting device

Observe the following requirements when
operating the circuit breaker lifting device:
• The wheels must be properly set on track.
• Do not depend upon the drum attachment to
support the full breaker weight.
• Allow 4-5 wraps of wire rope to remain on
the drum.
• Prevent snarling, kinking or knotting the
wire rope.
• Lift only circuit breakers.
• Do not alter the lifting device or the circuit
breaker lifting yoke.
• Never walk or stand under a suspended breaker.
• Do not leave a circuit breaker suspended.

Advertisement