NOTE: Make sure snap rings are seated in pin groove and closed
properly.
Correct
8.
Install new 8-32 x 0.500 self-threading Torx head screw
in end of new aluminum round bar. Torque to 18-20 in-
lb (2-2.25 Nm).
4-12
Incorrect
9.
Pull up on other end of round bar. Slide new poly roller
on bar.