Installation requirements and equipment

These instructions provide a systematic guide for installing and
commissioning the VersiCharge Ultra 175 unit.
The VersiCharge Ultra 175 unit must be installed and serviced by
qualified electrical personnel.
Observe all pertinent national, regional, and local safety
regulations when you install and commission the VersiCharge
Ultra 175 unit.
The VersiCharge Ultra 175 unit has an IP65 electronics enclosure
rating, however, as it must be opened for installation, this is
best done in dry weather, or under cover, to avoid moisture or
debris ingress.
The VersiCharge Ultra 175 unit must be properly installed,
assembled, and commissioned according to these instructions
before it is used.
10
In-box equipment:
• 5mm pin hex tool to remove the M8 security screws fixing
the plastic panels.
• 4mm Allen wrench to remove fasteners on the enclosure
access cover.
• 4x M32 cable glands.
• 1x M25 cable gland.
• M10 fasteners for wiring.
• External Ethernet connector.
Required equipment (not supplied):
• Lifting apparatus. See page 3 for weights. Ensure lifting
apparatus is sufficiently rated.
• 110mm OD Conduit
• 4x M10 lugs and crimping equipment for wiring installation.
• 4x site specific fasteners
• Fasteners are not supplied, as the type required depends on
the foundation used and must be chosen by the installer
accordingly.
• Socket set and ratchet
• Torque wrench with 30Nm setting
• Torque wrench with 2Nm setting
• 1 x M8 lug for ground wire
Document Key:
Items shown in blue are parts that require action for that
step.