Site configuration

Site survey:
A qualified engineer must survey the installation site to
determine the correct ground preparation for the size and
weight of the VersiCharge Ultra 175 unit, in accordance with
local regulations.
The VersiCharge Ultra 175 unit is best installed following the
recommended site configuration requirements.
Ground fixing:
The VersiCharge Ultra 175 unit is fixed to the ground through the
baseplate fixing holes with 4 x M16 fasteners or 5/8 inch
fasteners.
Fasteners are not supplied, as the type required depends on
the foundation used, and must be chosen by the installer
accordingly.
The fasteners should fix the VersiCharge Ultra 175 unit securely
to the foundation through the baseplate, in accordance with the
dimensions and fixing points shown in Figure 3: Base plate
dimensions.
Note: Keep the plastic inserts from the bolts for use in the
baseplate holes.
Conduit requirement:
Ø 110mm OD conduit.
When preparing the foundation, ensure that conduit and wiring
terminates above ground according to the document TRI125.
INS.016 Veefil-RT 175-S Piping and Cabling.
Installation Manual
Foundation requirements
The foundation must be flat, even, and have the appropriate
density for the weight of the VersiCharge Ultra 175 unit.
Check the flatness and level of the foundation and level of the
VersiCharge Ultra 175 unit baseplate prior to fixing.
Communications:
A site can utilize Ethernet or optical fiber between the IPU and
UU. If the UU and IPU are configured for use of optical fiber,
then use optical fiber. If not, use Ethernet (default).
4G network capability.
Cat 6a STP Ethernet cable required with a minimum length from
the foundation surface.
Fiber Optic Cable: OM3 Multi Mode 2 Core
For detailed wiring instructions, see reference.
| VersiCharge Ultra 175™