Level finished floor
Use the leveling screws to adjust the Clima Canal to the desired height. Make sure that the grill sits flush with the finished floor.
12
Fasten the floor brackets to secure the position of the trench.
14
If a screed is to be applied (poured floor or a cementitious screed)
rim insulation will be required around of the appliance; to protect it
and to cope with expansion differences during heating or cooling.
13
Fill up the cavity between the trench and concrete with wet cement
or spray foam.
Complete the electrical and hydronic connection.