Connecting the Switchgears
Use the default connection equipments M8x20mm bolts to connect the swithcgears together.
The connection points are located on side part of the switchgears. Side cover of the switchgears are mounted
for the first and the last unit.
Fixing the Switchgears
Remove the cable clamps and bottom sheet of the switchgear. Then use 4 fixing holes at the bottom of the
switchgear. After fixing the switchgear on the
floor.
Re-install the bottom metal sheet and cable clamps.