Lumascape Lighting Industries Pty Ltd
38-44 Enterprise Street, Cleveland, QLD 4163, Australia
PO Box 1875, Cleveland D.C., QLD 4163, Australia
T 07 3286 2299
F 07 3286 6599
E sales@lumascape.com.au
W www.lumascape.com.au
LS333ANS-2: Underwater Luminaire
Warranty void if not installed as per installation instructions
DANGER
ISOLATE LUMINAIRE FROM POWER
Failure to isolate power
supply before installation or
maintenance may result in
fire, serious injury, electric
shock, death and may
damage the luminaire.
Installation Preparation
1.
To aid installation of the cable the number of elbows
and bends should be kept to a bare minimum. Also,
using 25 mm conduit is highly recommended. Check
cable length required, taking into account voltage
drop and distance to transformer. NOTE: In Australia,
each luminaire must be installed as detailed in
AS3000 Clause 6.4.4.5
Power supply must be isolated prior to connection
or disconnection of cables. Failure to do so will
result in damage to the luminaire components.
Run Conduit & Water Proof
3.
Connect conduit to conduit entry with suitable
conduit sealant. Use supplied adaptor if necessary.
Run the conduit to the power supply above water
level and ventilate to prevent siphoning.
Figure 2
Figure 3
www.lumascape.com.au
The luminaire should only be used
complete with its protective
Do not shorten, interfere or
disconnect cable from luminaire.
Warranty will be void if cable
assembly is tampered with.
2.
4.
tighten gland
Copyright ©2013 Lumascape Lighting Industries Pty. Ltd. ABN 21 010 572 773
INSTALLATION INSTRUCTIONS
WARNING
shield (cover)
Installation Preparation
Locate niche in pool and wire to
reinforcing bars.
The 20 mm conduit entry
should be at top of niche (Figure
1). Although some variation is
accommodated by the outer cover
system on the luminaire, care
should be taken to position the
niche level and to allow for pool
finishing materials.
Install Temporay Shield on Niche
Fit fibreboard shield to opening of
niche before concreting (Figure 1).
Ensure no concrete enters niche.
tapped brackets
luminaire
INPUT VOLTAGE: 12 V AC
WARNING
AVOID HIGH
NO POWER
CHLORINE LEVELS
TOOLS
Figure 1
Concrete-in Niche
5.
Encase niche and conduit in concrete. Once in
place, finish surface of pool flush with front of
niche.
Concrete-in Niche
6.
Feed cable into niche, allowing sufficient free
cable in niche to allow the luminaire to be placed
on the poolside for re-lamping and maintenance.
A maximum of 1.3 m of cable can be coiled
inside the niche.
Terminate Luminaire
7.
Firmly tighten cable gland on the inside of
niche to seal cable entry (Figure 2). Connect
to a suitable power supply in accordance with
local wiring rules for connection and location
of supply. Where it is necessary to joint cables
underwater the connections and cables must be
IP68 rated
Install Lamp & Test Luminaire
8.
Open luminaire and install lamp as per re-lamping
instructions on next page. Test the luminaire for
correct operation.
Install Luminaire
9.
Coil free cable inside niche and install luminaire
in niche by screwing long outer cover screws
into niche brackets (Figure 3). Coil cable inside
luminaire with care. Do not double coils over, or
luminaire will be difficult to remove from niche.
Important Note
10.
Do not locate luminaire near heat sources.
Chlorine levels must be kept below 4 parts per
million. Higher levels may cause corrosion to the
luminaire and void warranty.
UNDERWATER
MODEL: LS333ANS-2
A.C.N. 0105 72 773
INSTALL AWAY FROM
OTHER HEAT SOURCES
fibreboard shield
finished surface
reinforcing bars
concrete
IN0040 - 23 October 2013
Need help?
Do you have a question about the LS333ANS-2 and is the answer not in the manual?
Questions and answers