D.4.3.8.

Mounting the AutoLinks in the three phase body

For each AutoLink place the hookstick in the tube's lower contact eyelet and mount in the isolating support body.
Withdraw the pole and place it in the tube's superior eyelet (See Figure 10). Push it until it remains in closing position.
REMEMBER! It is not recommended to close the AutoLink under load.
The line must be measured before to avoid closing under fault for safety reasons.
Figure 17.
Figure 18.